Water Corporation of Western Australia (Water Corp), the principal supplier of water and wastewater services to WA, have two (2) large-scale Water Desalination Plants, one of which is located at Binningup.  As part of the Southern Seawater Alliance (SSWA), Water Corp designed the Binningup plant to be constructed in 2 stages – both capable of producing 50 billion litres of water per year.

PowerEarth Technologies Pty Ltd were contracted by Water Corp to perform high voltage (HV) Earthing Design and Earthing Installation Verification testing for each stage of construction for this plant.  Specifically this involves soil resistivity testing, HV Earthing system design, Current Injection testing, plus Step Potential, Touch Potential, and Continuity testing for each of these stages.